Board Report: 2014-IT-B-002 February 7, 2014
Rec. no. | Report page no. | Recommendation | Responsible office |
---|---|---|---|
1 | 5 | Reevaluate the data center relocation budget, taking into consideration the design changes that have occurred, and implement a process for updating the budget as additional cost information is available. The updated budget should clearly separate build-out and operations expenses to allow for separate tracking and monitoring through the duration of the project. | Division of Information Technology |
2 | 8 | Continue to closely monitor data center relocation project schedule risks and identify and analyze possible approaches for responding to potential delays that could affect the Martin Building renovation project. | Division of Information Technology |